Case Study: Installation of Generators at Centre Parcs, Whinfell Forest
Project Overview
Logic was contracted by Centre Parcs to enhance the power infrastructure at their Whinfell Forest site. The project involved the installation of 10 new generators across various substations within the site. This case study highlights the planning, execution, and successful completion of the installation, focusing on the largest generator.
Project Details
Challenges and Solutions
Logistics and Transportation
Installation
Execution
The largest generator, a 1250KVA unit weighing 25 tons, was successfully lifted and positioned on-site. This critical step was completed on schedule, ensuring the project remained on track. The use of a 120-ton crane was pivotal in manoeuvring the heavy equipment through the site’s challenging terrain.
Outcome
The installation of the generators at Centre Parcs, Whinfell Forest, was completed successfully, enhancing the site’s power reliability and capacity. The project demonstrated Logic’s capability to handle complex logistical challenges and deliver high-quality results.